  1. Create/Maintain Plant Parameters for MRP (OPPQ)
  2. Maintain MRP Group Parameter (OPPR)
  3. Activate MRP and Set Up Planning File (OMDU)
  4. Order type Parameter (OPJH)
  5. Order type dependent Parameter (OPL8)
  6. Define Production Scheduling Profile (OPKP)
  7. Scheduling Profile (OPU3)
  8. Control Key (OP00)
  9. Availability Check Parameter (OPJK)
  10. Confirmation Parameter(OPK4)